July mine update

July 12th, 2012|

We are excited to announce that the plans we made to expand the recovery field at the Clavo Rico mine have begun to bear fruit.  As you can see from this photo the first level [...]

Recovery Field Progress June 2012

June 26th, 2012|

Recovery field and pond layout

June 12th, 2012|

The photo below shows the progress of the ore being loaded onto the recovery field at the Clavo Rico mine site (to the far right), and the various ponds that make up the rest of [...]

Video of Clavo Rico mine in operation.

May 31st, 2012|

This video is a montage of clips recent taken at the Clavo Rico mine site.  It gives an overview of the layout of the mine, and an up-close view of the mine operations in action [...]

Mine Update

May 17th, 2012|

The leaching process has been underway for nearly 10 days now and we are already seeing the rich pond filling with gold-bearing solution.  The gold ppm (parts per million) is currently being tested at roughly [...]

ADR plant weathers setbacks, is finally ready for shipping to mine site.

May 6th, 2012|

Following delays for the past few months, the ADR (Absorption, Desorption, and Recovery) plant is finally ready to be shipped to the site in Honduras.  It has been assembled and subjected to rigorous testing, and [...]